DT executed a subcontract with CDI Constructors/Hunt Joint Venture in November 2016. Mobilization of heavy equipment and personnel transpired the following week, December 5th, 2016. The scope of work incorporated demolition of 80,000 SF of building in a bowl configuration adjacent to the multi-million-dollar facility, along with demolition of the high-rise scoreboard structure. DT provided protection of the field surface at the north end zone, and constructed the heavy haul ramp that would be utilized by following trades upon completion of demolition. The contracted demolition scope was completed on schedule with haul off completing January 4th, 2017 just after the holiday season.

Location: 350 N Razorback Rd – Fayetteville, Arkansas

Start Date: December 2016

Completion: January 2017

Contact: John Teeter, CDI Constructors