Xerox Corporation Demolition:

Extruder and Grinder Building Decommissioning

Location:  Yukon, OK

Project Duration:  100 days

Scope of the project included the removal of the outdated grinder and extrusion building.  The equipment, structure, and foundations needed to be removed to eliminate the maintenance and liability associated with the structure.

The 100,000 square foot 4 story structure was attached to an occupied existing facility that remained in operation during the project.