Harris Hospital Demolition
Location: Newport, AR
Project Duration: 90 days
Scope of the project included the removal of the 110-bed hospital. The structure was retired upon completion of a modern facility. The removal of the cast in place concrete structure provided space for future expansion of the medical office buildings in the area.
The 3 story structure and the foundations were removed without disrupting business at the attached medical office building.